Acute Medical Unit – UHG

Acute Medical Unit

Client: University Hospital Galway, for HSE West

Project Description:

The work involved stripping out redundant finishes, fittings and services and replanning sections of the ground and first floor of the main ward block at UHG for use as an acute medicine and acute renal dialysis unit.

New mechanical and electrical services installation, including all associated builders work. Existing mechanical & electrical services were diverted & adjusted as necessary and new drainage runs were formed.

The sequence of works ensured the maintenance of hospital services during the currency of the project. Disruptive work was scheduled to avoid Hospital working hours which ensured daily activities were not interrupted.  As existing live services were required for the continuing operation of the Hospital, works were carried out without interruption to same.

Value: €719k

Completed: May 2012

Acute Medical Unit1 Acute Medical Unit2