Refurbishment & Extension Radiology Dept Connolly Hospital

Client: HSE Bridge West, Cherry Orchard Hospital

Project Description:

This project was undertaken in a phased manner. These phases comprised of:

  • Demolition of the existing porto-cabins to the north of the site and removal of porto-cabins in an area of future staff accommodation phase, following decanting to newly constructed staff accommodation area.
  • Diversion and protection of existing services in the area of the proposed extension to the south of the existing building.
  • Provision of temporary escape provisions for duration of the works, adjusted on a phased basis as works progress
  • Construction of new extension to the south of the existing building and associated works.
  • Construction of new extension to north of existing building and associated works.
  • Internal works within existing building.
  • Works to the waste compound area
  • Quench pipe – re-routing by specialist
  • Provision and installation of specialist equipment by specialist medical contractor

Completion Date: 21st June 2018