Careys were successfully awarded the Tender worth seven figures for this project, after a competitive process. The project comprised building an extension of the existing bedroom block and alterations and refurbishment to the pavilion bar and spa areas.
The works involved:
- New-build of 24 bedrooms, laundry room, store, lift and plant room.
- New single storey link hallway at ground level to connect the extension back to the existing building.
- Temporary emergency egress route through existing rooms and temporary external stairway for duration of Project.
- Installation of a new Lift in the existing building.
- Material alterations to existing pavilion building including the amalgamation of the ground floor bar and meeting room and conversion of second floor offices to spa treatment rooms.
- External works including hard and soft landscaping, new car parking areas, new surfaces and pathways
Throughout the project, the existing hotel and bedroom block remained fully operational and functioned as normal. This required detailed coordination and establishment of mitigation measure and controls to ensure minimal disruption to hotel staff and occupants.
Completion Date: September 2020